NERC Reports 85% Power Generation Capacity Utilisation in October

By wk-admin· 12 November 2026
NERC Reports 85% Power Generation Capacity Utilisation in October
Share:
 

 

 

By Wakirike Herald

The Nigerian Electricity Regulatory Commission (NERC) has reported that Nigeria's grid-connected power plants utilised 85 per cent of their available generation capacity in October, with average hourly electricity generation standing at 4,047 megawatts (MW).

The commission disclosed this in its October Operational Performance Fact Sheet, published on its official X handle on Wednesday.

The report provides an assessment of the operational performance of grid-connected power plants, including available generation capacity, electricity output, load factors and grid stability during the period under review.

According to the factsheet, average available generation capacity stood at 4,744MW, while average hourly generation reached 4,047MW.

The commission explained that this represented 85 per cent utilisation of the available generation capacity.

"Average available capacity stood at 4,744 MW, with an average hourly generation of 4,047 MW, indicating that 85 per cent of available generation capacity was utilised," the report stated.

Average Generation Declines Despite Improved Load Factor

NERC reported mixed movements in key generation performance indicators during October.

The commission said the average load factor increased by 4.16 per cent, while average hourly electricity generation declined by 1.02 per cent.

Average available generation capacity also dropped by 5.85 per cent during the month.

The figures indicate that although power plants utilised a higher proportion of their available capacity, the overall average electricity generated and the capacity available for generation recorded declines.

Jebba Records Highest Load Factor

Among the leading power plants, Jebba_1 recorded the highest load factor at 99 per cent, generating 423MW against an available capacity of 429MW.

Omotosho_1 followed with a 97 per cent load factor, producing 179MW from 183MW of available capacity.

Afam_2 ranked next at 94 per cent, generating 371MW against an available capacity of 395MW.

Other leading plants included Egbin_1 and Ihovbor_2, which each recorded 93 per cent load factors, while Shiroro_1 achieved 89 per cent.

Delta_1 and Kainji_1 each recorded 84 per cent, while Okpai_1 posted 78 per cent.

Odukpani_1 recorded the lowest load factor among the listed top-performing plants at 66 per cent, generating 202MW against an available capacity of 305MW.

NERC Raises Concerns Over Grid Frequency Stability

Beyond generation performance, the commission identified deviations in the national grid's operating frequency during October.

According to the factsheet, the average lower grid frequency was 49.46 hertz (Hz), while the average upper grid frequency stood at 50.66Hz.

Both figures fell outside the prescribed operational frequency range of 49.75Hz to 50.25Hz.

Grid frequency stability is essential for maintaining the balance between electricity supply and demand and ensuring the reliable operation of power infrastructure.

Deviations from the prescribed range can place pressure on electricity network equipment and affect the stability of power supply.

Grid Voltage Also Exceeds Prescribed Limits

NERC also reported deviations in the grid's operating voltage during the month.

The average lower grid voltage was recorded at 305.00 kilovolts (kV), while the average upper voltage stood at 353.94kV.

These figures were outside the prescribed operational range of 313.50kV to 346.50kV.

The findings highlight continuing operational challenges beyond electricity generation, particularly in maintaining stable transmission and distribution conditions across the national grid.

Generation Capacity and Grid Stability Remain Key Challenges

The October performance figures provide an indication of both the utilisation of Nigeria's available generation capacity and the technical challenges affecting the electricity system.

Although the reported 85 per cent capacity utilisation suggests that power plants generated a substantial proportion of their available output, the declines in average hourly generation and available capacity remain important considerations.

The deviations in grid frequency and voltage also demonstrate that electricity generation alone does not determine the reliability of power supply. Transmission infrastructure, grid balancing and distribution capacity are equally important.

For electricity consumers and businesses, the central concern remains whether improvements in generation performance can translate into more consistent and reliable electricity supply.

Sustained investment, effective grid management, maintenance of power infrastructure and improved coordination across the electricity value chain will be necessary to address the challenges identified in the regulatory report.