FG Targets December Inauguration of Kaduna–Kano Rail Line as Construction Advances

By Wakirike Herald
The Federal Government has expressed satisfaction with progress on the Kaduna–Kano railway project, reaffirming its expectation that the long-awaited rail corridor will be inaugurated in December 2026.
The Ministry of Transportation disclosed that construction work, including facilities at the Kano terminal station, had reached an advanced stage following an inspection by senior government officials and representatives of the Debt Management Office (DMO).
The ministry's Permanent Secretary, Funso Adebiyi, made this known during an inspection tour involving a train journey from Jaji in Kaduna State to the Kano Terminal Station.
According to a statement issued by Osima Seddon, Assistant Director of Press and Public Relations at the Federal Ministry of Transportation, Adebiyi described the journey as smooth and commended the quality of work delivered by the contractors.
He said the Kano terminal was substantially ready, with the installation of its name signage remaining among the outstanding tasks, expected to be completed within two weeks.
Safety and Quality Improvements at Railway Stations
Adebiyi explained that some adjustments had been made following his previous inspection to ensure that the project met required safety and operational standards.
One significant improvement was the replacement of toughened glass with laminated glass in areas accessible to passengers.
He said laminated glass offered better protection because it was less likely to break into dangerous fragments when damaged.
The permanent secretary also disclosed that station lighting bulbs had been replaced to meet a minimum serviceability requirement of three years.
Other improvements included the installation of man-lifts to support maintenance operations and arrangements to train Nigerian Railway Corporation (NRC) engineers in station management and operations.
He said the NRC had been directed to nominate engineers for the training, which he would personally attend. Only candidates who successfully passed the required examinations would be retained to operate the facilities.
Three-Month Test-Run Proposed Before Commercial Operations
On the commencement of passenger services, Adebiyi disclosed that the ministry was proposing a three-month test-run of the railway between Jaji and Kano.
The exercise could involve free passenger transportation, subject to approval by President Bola Tinubu.
He explained that the proposed test-run would allow the authorities to evaluate the railway's structural integrity, safety and operational performance before introducing full commercial services.
Adebiyi expressed confidence in the quality of the track infrastructure, citing the smoothness of the inspection journey as evidence of the standard achieved.
He noted that passengers could comfortably drink beverages and eat during the journey without experiencing noticeable vibrations or shaking.
However, the proposed test-run and free passenger arrangement remain subject to presidential approval.
Kano Terminal Designed to Accommodate More Passengers
The permanent secretary also highlighted improvements aimed at making the railway facilities accessible to a wider range of passengers, including persons with disabilities.
He disclosed that approximately four lifts had been ordered to improve accessibility, while an additional staircase had been introduced at the rear of the Kano terminal.
Railings for the staircase had also been imported to ensure safer movement within the facility.
Adebiyi described the terminal's waiting hall as exceptional, expressing confidence that it could rank among the best railway terminal facilities in Africa.
Meanwhile, the Kaduna station is undergoing expansion to accommodate the anticipated increase in passenger traffic.
Jaji Bridge Remains a Major Outstanding Infrastructure
Despite the progress recorded, Adebiyi identified the bridge near Jaji as a major outstanding infrastructure component required to complete the connection towards Kaduna.
He explained that security considerations around Jaji had necessitated a horizontal curve in the railway alignment, making the construction of a bridge necessary.
According to him, the bridge is being constructed in situ and has reached an advanced stage of completion.
Track-related works have progressed to the bridge embankment, with rail installation expected to commence after the structure is completed.
The completion of this section is important to establishing the continuous railway connection between Kaduna and Kano.
Government Expands Railway Connectivity Beyond Kano
Adebiyi also disclosed that construction was ongoing on another railway corridor originating from Kano and extending through Kazaure, Daura and Katsina.
He acknowledged that land acquisition challenges had affected the section between Kano station and Dawano but said work along the alignment from Dawano through Kazaure and Daura to Katsina was progressing.
Providing a broader picture of the government's railway development programme, he explained that the Kaduna–Kano corridor formed part of an integrated national railway network intended to connect major commercial and industrial centres.
He cited the existing railway connection from Apapa in Lagos to Ibadan, where a dry port provides cargo clearance facilities, as part of the wider strategy to move 40-foot containers by rail.
The planned network is expected to connect Abuja to Kaduna, Kaduna to Zaria, Zaria to Kano and extend towards Kazaure, Daura and Katsina.
Adebiyi expressed optimism that the proposed connections would eventually enable passengers to travel by rail from Warri through Kano, Katsina, Daura and Kazaure, with further connectivity towards Jibia and Maradi in the Niger Republic.
Such an expansion could improve passenger movement, facilitate cargo transportation and strengthen commercial links across several states and neighbouring countries.
Debt Management Office Commends Project Progress
Also speaking during the inspection, the Director-General of the Debt Management Office, Patience Oniha, explained that the agency played an important role in providing funding and financing support for government capital projects.
She said the inspection was organised to enable the DMO leadership to assess progress on infrastructure investments supported by government financing.
Oniha recalled that during an earlier visit, the delegation travelled by road from Kaduna to Kano.
The latest inspection provided an opportunity to experience the railway journey from Abuja through Kaduna and Jaji to Kano.
She commended the Federal Ministry of Transportation and the contractors for their efforts towards delivering the project.
Representatives of the China Civil Engineering Construction Corporation (CCECC), including Project Coordinator Mark Xu, and Team Nigeria Consultants' Project Manager, Precious Ebare, also reaffirmed their commitment to completing the work in line with international design specifications.
They said quality assurance measures and corrections arising from previous inspections had remained central to the project's implementation.
Delivery and Operational Readiness Remain Key Tests
The anticipated December inauguration represents an important milestone in the Federal Government's railway expansion programme. However, the successful completion of the remaining bridge infrastructure, installation of essential facilities, safety assessments and operational preparations will determine when the corridor can fully serve passengers.
The proposed three-month test-run could also provide an opportunity to identify and address operational challenges before commercial services begin.
For communities and businesses along the Kaduna–Kano corridor, the project's eventual completion could create additional transportation options, improve movement between commercial centres and support economic activities.
The next critical step is to translate the reported construction progress into a fully completed, safe and reliable railway service.
Wakirike Herald
The Voice of Wakirike People Everywhere
Written by
wk-admin
Comments
- Be the first to comment.